In Colorado, the building code asks for a fire block when finishing a basement. I know this goes against the out walls (foundation). I've seen 2×4 and OSB used: which is better? And how does the OSB get installed?
Basement – How to install fire blocking while finishing a basement
basementcode-compliancefireproofmunicipality
Related Topic
- Basement – How to fix a small slightly damp area in the basement wall
- Basement – How to find out if a vapor barrier is requried for finishing a basement to code
- Basement – Horizontal fire blocking when using rigid foam in basement
- Basement Refinishing – Importance of Moisture Barriers in Finishing a Basement
- Basement – Should I frame out the foundation walls before or after I install the subfloor
- Basement – How to insulate basement walls and floor after water mitigation
- Insulation Requirements – Plywood Over Rigid Foam Fire Barrier Compliance
Best Answer
OSB would be easier and faster, it gets installed BEFORE the top plate goes up. If you plan to use 2X4 framing set 1" away from the wall or if you follow the detail provided in another post, you can still use it as fireblocking.
When you layout for your top plate and chalk your line for setting the top plate by, before you do, measure over to sill plate that the joists set on for the dimension to rip the OSB. I would suggest to rip the OSB a little shy of the chalk line. that way you will always have it as a reference. My carpenters had ripped the plywood wide enough to cover the line to supposedly follow it but when the wall was finished framed it had a 1/4" bow in it.
Set the plywood, then the top plate, and build the rest of the wall.