Basement – How to support second-floor beams when replacing posts in the basement

basementframing

We are excavating our half basement and need to replace the support posts with new ones on new footings. The problem is that 2 of the 3 posts also extend to the 2nd floor. We can't just jack up the joists with temporary shores as in most cases because the beam would be unsupported.

The post goes from the footing block straight up to the 2nd floor and would not be supported by the joists except by nails around it.

enter image description here

This video shows it in the first part.

Best Answer

You're correct, there is no way to do this all from the lower level. Add temporary support to the beams in the basement, then go up a floor to the main level and take the load off that post with temporary supports to transfer the load to those beams.