Is my contractor guy doing a botch up job with repointing.
Is it normal that it's drying out all cracked up like this and it's easy to crumble.
They are only using the masonry cement type S and color are they supposed to be mixing it with sand to strengthen? Is this just the first layer? So was able to add screen shots
Concrete – Is the contractor guy doing a botch up job with repointing
brickconcretemasonry
Related Topic
- Should custom masonry mixes first be mixed dry
- Conflicting contractor opinions on rebuilding steps using original construction method
- How much active labor is involved in repointing
- Concrete – How much water for mixing with concrete
- Concrete – Contractor is installing a vinyl fence and posts but is not using any water with concrete. Is he doing it right
- Will repointing solve water leakage issue
Best Answer
That is terrible and unacceptable.
The mortar has been mixed with too much water causing it to dry (cure) and crack. When mixed, it should be the consistency of thick paste. There should be no water oozing out when mixed and sitting on the board before “placed”.
Cracking will allow moisture infiltration. It’s useless. Remove it and re-do. Do not just reapply another drier coat over the cracks. (Type S is acceptable for above grade use.)