Concrete – Is there enough time to pour 40 sqf 4″ slab with 60lb bags of premixed concrete if working alone? Any hints

concreteslab

I am planning to pour 40 square feet of 4" slab to support light shed. I was thinking of using 60LB bags of regular premixed concrete (not fast set). I figured that getting it as ready mix in a truck is way too expensive and also the site is 150+' away from the street.

What is the best way to do it so concrete wouldn't set before time and I don't kill myself? The place is very constrained so I can't fix electric mixer and it's tight even for wheelbarrow. My current plan is to use Leonard OdJobâ„¢ Concrete mixer and I will need abot 30 bags.

Any alternatives and hints?

Best Answer

The answer depends on your level of physical ability and ambition, and is therefore mostly subjective. There are plenty of folks who could do it. I wouldn't try it myself at my age and level of fitness. Concrete is really freaking heavy. I would want some additional labor on hand.

I attempted to finish a sidewalk and garage apron on my own when my help had to leave, and there's little as nerve-wracking as finding oneself racing the clock with setting concrete. You never end up with a good finish in those cases, and if you try something foolish like watering the mix you'll end up with a weak surface prone to flaking and disintegration.

My $.02: Play it safe and have someone around to help you mix and move the mud.