When laying a second layer of plywood subfloor to support granite tiles, does the original plywood subfloor need to be leveled first or just level the floor after adding the second layer? I have about a 1/4” dip.
Also, if the new layer is 3/8” plywood, is it necessary to remove the toilet flange, or is an extender sufficient?
Best Answer
Since you are after subfloor strength I think you'd want to level after you put the other layer down. I assume you are gluing and screwing the 2nd layer to the first.
TCNA typically wants 1 1/4" thick subfloor. After you install your 3/8" ply do you meet this thickness?
This sounds like a bathroom how big is it? Are your floor joists sized for L360? How large is the area that dips 1/4"?