Load-Bearing Wall – Can Bottom Wall Plate Be Removed After Installing New Header Beam?

load-bearingremodeling

I removed a section of load bearing wall in my house and installed a new header in the opening. The 2×4 at the bottom of the wall was not removed and sticks up above the surrounding flooring (~3/4" on one side and ~1/4" on the other).

The guys refinishing the floors want to remove the 2×4 so they can gradually build up between the two floor levels.
Does this sound safe?

The house is one storey built over a crawlspace, and the jack/king studs for the new opening do not sit directly over a floor joist.

Best Answer

If there's no wall there need be no plate. It should remain under any trimmer studs supporting the header, of course. Cutting it out flush with the rough opening is standard practice.