I'd like to build a French cleat storage system on an exterior wall in my basement shop, but am concerned about whether the cleats will have sufficient support given the construction of the wall. The wall is constructed of 3/4" drywall over lath and plaster (~1/2" of plaster over 3/8" laths), with additional 1/4" and 3/4" boards between the laths and the studs.

My current plan is to use 5/16" x 5 1/8" structural screws (rated as equivalent to a 1/2" lag bolt) to attach the cleats, two per cleat per stud, as shown in the diagram below. (I have not shown the screw details because my Sketchup skills aren't quite there yet.) The structural screws will be countersunk 3/16" since they have a washer head.

enter image description here

A photo showing the actual materials (minus the stud, which is covered by insulation, and the drywall, which is not visible in the area where I have this cross-sectional access):

enter image description here

I have questions on a couple aspects of this:

1) Will the 1 13/16" depth of the screw in the stud provide sufficient withdrawal resistance?

2) Can I rely on any of the intervening material to provide any support as far as shear resistance, or do I effectively have about 2 1/2" of unsupported screw? And if the latter, can this possibly hold any significant weight? If not, do I have any options other than a) not doing the project or b) completely ripping out the drywall and lath and plaster to secure the cleats more directly to the studs?

3) Would using a toggle bolt into the lath-and-plaster between the studs be wise in addition to (or instead of) the structural screws into the studs with such a long unsupported length?

Thanks!

EDIT: Additional information requested by commenters:

  • I have had some (modest) success using a small metal detector to locate the nails in the laths. I have first located the drywall screws and then used those as a guide to locate the lath nails; they register faintly but some do register. My plan was to mark these and then drill small test holes to ensure I hit a stud at the expected depth rather than a cavity (I expect I might need to do 2-3 per stud to ensure I can find the center).
  • The studs are spaced approximately 16" o.c. in other parts of the basement where the lath and plaster has been cut away sufficiently for me to visually inspect them. I say approximately because there seems to be some variance of up to 1/2", and in at least one case the distance is 22". The nails/screws I have been able to locate in this wall are also approximately 16" o.c.
  • The studs themselves are 2×6; they are slightly larger than today's 2x6s as I believe they date from the original construction of the house in 1900. Most of the house has been remodeled or added on to, but this side of the basement is mostly original except for the addition of the drywall, which obviously is much newer.
  • I plan to use the cleats for hanging various power tools, accessories, clamps, etc. I would expect the total weight per cleat per stud will not exceed 100lbs. But more accuracy here is probably desirable.
  • Lastly, sadly, yes, Seattle is definitely in a seismic zone. My plan was to follow a suggestion I saw from someone who built French cleats in California who used some short cut-off nails inserted in an angled hole in the back of the shelves such that they protruded just below the cleat to prevent upward movement that would cause the cleat to "jump off", but could be easily removed to reposition it.

Best Answer

My guess is that the screws you want to use won't work well if the shelves are heavy. The embedment in the stud is too shallow and the screw will flex quite a bit. I think the shaft of the screw is too small for the drywall and plaster to provide much support in shear.

I'd simply strip off the drywall and screw 3/4" plywood on top of the plaster. I'd nail on a pressure treated 2x4 like a base molding so the plywood isn't in contact with the floor, and rest the 4' edge of the plywood on the 2x4 before attaching. This way the weight is carried by the plywood rather than the nails.