I have a decent sized hip truss package coming. It's about a 60' wide by 30' deep building with 2' overhangs. Hip style with 4/12 slope.
I have only helped before in setting trusses but never doing them where I am in control. I was wondering which one to set up first, especially since we will do them by hand. If we had a lift or crane, I'd just work my way from one side to another but since we set them by hand our only lift is a machine to lift to the edge of the wall and then we have to drag them to position.
Knowing this, should we start with the middle most truss and work to the edge? Or should we still start with the double girder/header/bridge truss that starts about 8' back from the end, and has all the small jacks tie into it?
Best Answer
You'll receive diagrams showing critical points to hit, such as the first full-depth truss from one end.
Modern hip truss sets typically have a view different types of trusses, depending on size and the existence of jogs in the building outline. From one end to the center:
We normally work from the first full-depth truss (the girder for the shorties) and go right across the building. This allows you to either boom or walk each truss into position without obstruction. You should do what makes sense for your jobsite and crew capability. If you don't have two people comfortable walking walls, you may need to slide them up in the middle of the building.
It's a bit of an art to get those overlay systems on plane. Look things over from the ground regularly and adjust the stepped trusses as needed. Seek to get straight ridges, which are one of the most conspicuous aspects of a roof.
Add a diagram to your post for more specific advice.